Status Report Week Ending August 24, 2007: Completed backfill and pile caps; continued forming Level 2 ; Begin level 2 rough-ins for mechanical, electrical, plumbing; completed excavation and began pile installation on parking facility.Level 2 rises!Parking Area - Beginning Pile Installation