Towers On The Grove - September 2007 Progress Reports
By TowersOnTheGrove Phase1 | Published  09/7/2007 | Towers On The Grove Phase 1 | Unrated
Week Ending 9-21-07

Week Ending 9-21-07 - Tower - Placed level 4 slab, MEP level 4, verticals to level 5, started masonry on level 2



Ever seen cranes dance?!
Week Ending 9- 21-07 - Parking: erected tower crane, continuing pile caps, started backfill, started wall forms