Week Ending November 30, 2007


Boulevard View
Week Ending November 30, 2007: Placed Level 13 slab, pouring vertical to Level 14; masonry started level 10, started windows level 2 and 3


Parking Deck: Placed Level 4 slab; forming/pouring columns to level 5



Metal Studs - Level 8